Antonov An-70
a new generation tactical
transport.
Although
plagued by lack of investment and the loss of the first prototype in a mid-air
collision, the An-70 is proving to be a highly capable transport aircraft. So
much so, as Paul Duffy reports in his analysis of
"Antonov first entered the military transport scene in
1956 with its twin turboprop An-8. This was designed to carry either a tank or
paratroops, and to offer the Soviet forces a similar capability to that of the
Fairchild C-119, but less than that of the then new Lockheed C-130 Hercules.
The An-8 soon proved itself, but a relatively small production of just 150 followed
because the Soviet military authorities quickly sought a larger aircraft more
capable of matching the performance of the growing numbers of Hercules entering
service with the US Air Force and its allies. A little more than a year after
the first flight of the An-8, its larger brother, the four-engined An-12, flew.
This aircraft went on to become the standard military transport of the
Antonov has specialized in military transport ever since,
and many of its aircraft have also been developed into civil versions. Based in
the Ukrainian capital,
One of the new Antonovs is the An-70, (the other two are
the An-38 and the An- 140) and both the aircraft and its story are remarkable.
It started when the Soviet Air Force (VVS) began to look
for an An- 12 replacement in 1979. By then, the An- 12 had already been in
service for 20 years. Production in the
Antonov was one of three design bureaux asked to submit
proposals to the Soviet Ministry of Defence for the replacement, and the
bureau's general designer Oleg Antonov asked his deputy Vasili Teplov to become
chief designer for the work. However, detailed design requirements were not
issued until 1987: Antonov's successor, Piotr Balabuev, confirmed Teplov as
project leader.
Stringent requirements were laid down: the 30 years since
the An-12 had been conceived had seen considerable advances, not only in
aviation technology - annoured tanks and personnel camers had also grown in
size, weight and capability. The new specifications required the aircraft to
carry some 300 soldiers, or to airdrop 110 paratroops. It had to be able to
lift bulky cargoes, including modem tanks, artillery and other military
equipment and to have the ability to land and take off from short, soft strips.
Short take off and landing (STOL) capability was regarded as essential. It was
also required to have operating economics to a standard appropriate for the 2 1
st century, the first time this requirement had been sought in a Soviet
military aircraft programme.
The new aircraft would also need to be adaptable in order
to fill possible roles as a tanker, airborne early warning aircraft, and for
patrol operations. From the start of 'serious' design, the Antonov team saw it
as a possible replacement not only for the An- 12, but also for the C- 130 and
the Transal I C. 160.
Configuration
Teplov and his team began by adopting a similar concept to
that of the An- 12: a four-engined high wing design was considered necessary to
allow operations from unpaved runways, including the grass strips or dirt
tracks that would be needed for battlefield support. A wide body was dictated
by the need to carry modem military armored vehicles, but the choice of engines
was more difficult. For the first few years, money for the new aircraft came
from the
The research institutes involved in this work included the
Central Aero and Hydrodynamics Institute (TsAGI), which carried out the
detailed aerodynamic studies for the programme. The Central Institute of
Aviation Motors (CLAM) helped to design and develop the engine requirements,
and the Stupino Propeller Design Bureau (now called Aerosila) was given the
task of designing the propellers and gearboxes for the new Antonov. An earlier
Stupino design had allowed the Tupolev Tu-95 Bear and the world's first
wide-body, the An-22, to fly at speeds considerably higher than was thought
possible by Western specialists of the time. This was achieved by developing a
gearbox that reduced the rotation rate, and by widening the chord of the
propeller blades.
Materials were developed by other researchers: the All-Union
Institute of Aviation Materials (VIAM) worked on the new composites and
glass-fibers needed, while the All-Union Institute of Light Alloys (VILS)
developed solutions to the metallic requirements.
Work undertaken by the Siberian Scientific Research Institute
(SiBNIA) confirmed that the An-70 would be able to meet its operational life of
45,000 flight hours or 15,000 cycles.
Aerodynamic design
Teplov and his team teased that the aircraft's success
depended on designing a wing that would be efficient at the relatively high
cruise speed of Mach 0.68/0.70, whilst being capable of generating the high
lift necessary for STOL operations. The early work was carried out in
TsAGI's wind tunnels were also used to develop the new
Aerosila contra-rotating propeller, the l4ft 9in (4.5m) diameter SV-27. Each
propeller has eight blades on the forward shaft, which turns anti- clockwise,
and six on the rear shaft, which rotates clockwise.
A wide propeller chord, combined with a suitable engine
gear ratio, ensures that the maximum airspeed required is achieved without the
tip speed exceeding the critical Mach number for prop noise. The
contra-rotating system also gives an excellent balance, and there is no
tendency for asymmetric swing on takeoff or landing. The propeller pitch is
fully variable and may be feathered.
A close study of the propeller wash, or 'propwash', showed
it could be used to advantage for short field operations. With the propellers
mounted just forward of the wing, a 'Coanda effect' results. This allows the
flaps to maximize low speed lift, and with a glide slope angle of up to eight
degrees, the threshold/ final approach speed drops to about 95kts (176km/h).
Touchdown speed is as low as 76kts (140km/h). For a normal landing, final
approach is at 132kts (245km/h). While the nominal full flaps setting is 65*,
the outer portion lowers to 80' to take full advantage of the propwash. The
propellers were deliberately mounted higher than the fuselage doors to allow an
unimpeded exit for paratroop operations.
As was usual for the manufacture of large wings in the
End of government investment
The
The Soviet government selected the Ivchenko Motor Design
Bureau, at Zaporozh'ye in the
The VVS requirement called for a five-crew cockpit to
include a pilot, co-pilot, engineer, navigator and radio operator.
Elektroavtomatika developed a panel to give flight data, engine, system, and
instrument information on six 77/8in (200mm) square screens. When
Flight control system
Antonov was the first aircraft designer/ manufacturer to
introduce a fly-by-wire system on a transport aircraft; the An-124 Ruslan which
made its first flight in 1982. It was, therefore, a logical choice for the control
systems on the An-70, so Teplov's team developed what they term a 'second
generation' system for the new transport. The system is not exactly the same as
that used in the West, but in DASA:s audit, it was regarded as being
equivalent. ('Equivalent' is a term used in certification issues to indicate
that, although not directly in accordance with the airworthiness requirements
of that country/ region's authorities, the system is satisfactory in terms of
reliability and function and should meet all operational needs). Teplov has
provided five systems to cater for failures - four are fly-by-wire, and the
fifth is hydraulic. To reduce vulnerability to battle damage, the flying
control surfaces - rudder and ailerons - have been divided into several sections,
with three for the rudder and four for the flaps on each wing.
The Samara-made undercarriage assembly features three axles
on each main unit, with two wheels on each axle, to reduce the footprint load
(to 71lb/ft2 [5kg/cm2]) for operation from unprepared grass strips. Teplov says
that this gives the An-70 an advantage over the FLA.
"Both aircraft could airdrop supplies or equipment to
ground forces in battle conditions with equal accuracy. However, in many
situations, the An-70 could land close by and allow surface delivery, if
needed. In some situations, this could be a decisive factor."
As a design bureau, Antonov's task is not to build
aircraft, but to take responsibility for its design and solve any problems
arising during manufacture and operation. In Soviet times, a design bureau
would only build an aircraft for test purposes: this meant that the prototypes,
including the static and dynamic test examples, were built by the bureau, and
all subsequent production examples were built in a designated production
factory. Thus, Antonov built two prototype An-70s, one for flight test and the
other for static tests. It entered into a commercial arrangement with two
factories to manufacture production aircraft: Aviant in the Ukrainian capital,
Kiev, and the Russian factory Aviakor, located in Samara.
The flight test aircraft was completed in autumn 1994, and
following taxi trials and initial engine and systems tests, it made a
successful first flight on December 16 that year. As was normal for Antonov
first flights, this was simply a ferry from the design bureau's airstrip to the
test center at Gostomel, a distance of some 13nm (25km).
Loss of first prototype
Financial shortages slowed down the flight programme, and
the fourth flight did not take place until early February 1995. As was normal
for an early test flight, the An-70 was accompanied on the sector by a chase
'plane, in this case an An-72. Weather was not ideal, and the two aircraft lost
sight of each other and collided. The An-72, although damaged, landed safely
but the prototype An-70 was destroyed and its seven crew killed.
A difficult time followed for the Ukrainian design bureau
and its staff. Money continued to be scarce and the morale was low.
Nevertheless, the first three flights had convinced Balabuev and Teplov that
the design was a good one, and they fought to keep the programme alive. They
consulted their partners in the project, and receiving full support from them
all, decided to keep going.
TAPO Tashkent began the manufacture of a second wingset
while Teplov and his team took the second An-70 fuselage, originally planned
for static testing, and returned it to full flying specification. Another
fuselage was subsequently constructed for the static test programme. Twenty-six
months later, the An-70 was flying again, and the test work began in earnest.
Although the principal certification programme was for the
military, Antonov decided to carry out a civil programme in parallel. With a
great deal of commonality between the Soviet/Russian/Ukrainian military
certification and the Avia Register of the MAK (Interstate Aviation Committee -
(ARMAK), the new regulatory authority of the countries of the Commonwealth of
Independent States) AP-25 programme, this made sense. The AP-25 rules were drawn
up to correspond as closely as was practical with the West's Federal
Airworthiness Requirement FAR-25 and
On
Flight tests
So far, the flight tests have included handling
characteristics, high incidence and stall tests, and take-off, climb, approach
and landing tests. This last section includes investigation of STOL
performance: approaches have been made at glide slope angles of up to 6*, and
tests will continue up to 8*.
In the early tests, and with a take-off weight of 110 tons,
a rate of climb of 4,900ft (1,493m) per minute was achieved. In landing trials,
the STOL ground roll was just under 1,000ft (300m). So far, all trials have
been made with 12 tons of test equipment on board, mounted on an upper deck
which can also be used to carry troops or light cargo.
Fuel consumption during the trials has been measured at
between 3 and 3.5 tonnes per hour, including take-off, climb, cruise and
descent phases. In level flight at 16,000ft (5,000m), it is 3 ton - well under
half the fuel bum of the rival Ilyushin Il-76TD. The cruise flight level in
service is expected to be in the region of 26,000- 33,000ft (8-10,000m) and the
maximum cruising altitude should be 39,000ft (12,000m): at these altitudes, the
fuel bum should reduce even further.
Despite its use of propellers, the An-70 flies at speeds
not much below those of turbojets. Cruise is in the 405-432kts (750-800km/h)
range, only 27-54kts (50- 100km/h) lower than that of the Il-76.
At the time of writing (October 1999), the test programme
was concentrating on ground handling and engine tests intended to prolong the
service life. As both the airframe and the engines are new, Antonov and
Progress are working as a team to achieve certification of their products.
These include the many newly developed components and systems such as the
avionics.
Antonov is also planning to develop a civil version of the
An-70. With the International Civil Aviation Organization Chapter III
regulations coming into force in 2001, most of the large fleet of Ilyushin
Il-76 freighters serving with the airlines of the CIS countries will not be
welcome in many western countries. While they will have no noise-related
problems flying in their home regions, the loss of revenue from charter work to
western Europe and the
A twin turboprop variant is also under consideration.
Although this would have payload restrictions, it could be developed if Antonov
finds customers for it.
The principal market for the An-70 will be military
operators. Antonov calculates dig some 3,500 An-12s, C- I 30s and Transalls
remain in service, and while the Ukrainian aircraft would not even be
considered by some countries in the market for a replacement, it still leaves
considerable opportunities. Antonov believes that the An-7X will be some 40%
cheaper than the European A400M. For the 288 aircraft NATO requirement, this
equates to eight to ten billion ECU/Euros, giving the An-70 a price tag not
much higher than that of a similar number of C- 130.Js but offering a greater
capability. The company is now planning a support programme for the export of
An70/7Xs, building on experience it gained, in conjunction with Air Foyle and
Rolls-Royce, when it offered the An- 124- 100M to the Royal Air Force. On the
An-7X, the Antonov partners would work with western companies from
As a result of interest from other countries, the An-70
partners have formed the Medium Transport Aircraft International Consortium to
market and support the aircraft.
The An-70 was conceived for the Soviet Air Force (VVS),
although this has been succeeded by the air forces in the individual countries
of the former
The major problem facing the An-70 is lack of finance.
Piotr Balabuev has managed to keep the programme alive by carefully investing
the design bureau's commercial earnings in new aircraft. However, to keep the
programme running to schedule will require further funding, and this must be
the design bureau's major priority for the next few years."
|
Antonov
An-70 Specification |
|
Powerplant: Four 14,000shp (10,440kW) Progress/Motor Sich D-27
propfans driving scimitarshaped, reversible-pitch Aerosila SV-27 l4ft 9in
(4.49m) diameter, contra-rotating propellers, each with eight composite
blades at the front and six at the rear. |
|
Performance: Maximum speed: Mach 0.73. Normal cruise speed 405-432kts
(750800km/h). Low altitude cruise speed 297kts (550km/h). Maximum range: (35
ton payload) 940nm (3,600km); (30 ton payload) 2,700nm (5,000km); (20 ton
payload) 4,00nm (7,400km). Max operating altitude 39,370ft (12,000m). |
|
Weights: Maximum
take-off weight: 286,000lb (130,000kg). Empty weight: 145,500lb (66,000kg).
Maximum payload: 103,600kg. |
|
Dimensions: Length 133ft 0in (40.55m). Wingspan 144ft 61/2in
(44.06m). Height: 53ft 13/4in (16.20m). |
|
Accommodation: Three flight crew (two pilots and a flight engineer) plus
loadmaster, although it can be converted for two-crew operation. Pressurized
cargo compartment will accommodate a wide range of rigid or flexible pallets,
containers, unpacked freight, wheeled or tracked vehicles or seat up to 170
troops." |